Saturday, January 5, 2013

January 5, 2013: Scratch coat, sewer clean-out

Also, more wallboard...

The scratch coat is going on today.  They've prepped the house.

The mixer.  Everything is covered in plastic because the scratch coat material is like cement glue.

Outside the family room in the back is coated.

A view of the entire rear of the house.  Mostly not covered yet.

This is where the new and the old meet.


The chimney on the roof is getting covered too.

The south side.  The two story section was done first.

This is a close up of the corner treatment in preparation for the square corners.


Not the sharpest focus, but the left wallboard is QuietRock and the right is standard 5/8 wallboard.  You can see the sandwich in the QuietRock.
This is a shaper end-on image of the QuietRock.  Nearly the entire wall where the TV will be mounted is covered in this material.  Also, on the other side of the wall.

After much digging, the terra cotta for the sewer was found.  New terra cotta was installed for a clean out (as per code).


This is Matt gluing in the ABS sewer pipe from the house to an ABS fitting that is clampoed to the terra cotta.

The scratch coat is complete.  Alex and Cali are checking out how it looks wet, but it's now very hard.

The entire front of the house with the south side.

The north side is covered.

The back of the house is almost covered.  I believe the are waiting for the glass block windows to be installed upstairs be fore completing the scratch coat around them.

Another pic of the front.  The large pile of gravel is for the sewer pit.

Inside, the family room is boarded.  I got a sample of a 5 1/2 inch baseboard.  I think this is the right scale for this room.

This is Cali's room.  It's complete.  The QuietRock sections can be identified with the brown lines.

Alex's room is also boarded.

A picture of the blocking I added to the pocket door.  We should now be able to mount towel bars.  I just need to make sure my screws are never longer than 1 1/4 inches.  The blocking is 3/4 inches.  The wallboard is 5/8 inches.  So, 1 1/4 inch screws give me 1/8 inch margin.

The south side. The interleaving of the old and new stucco can be seen.

The two story section.

Another pic of the south side from the other direction.  Note: The white window will be painted to match the others.  It's a hold-over from before the remodel. It's a triple pane Pella that we wanted to reuse.

Thursday, January 3, 2013

January 3, 2013: Stucco prep and more wallboard

Evan doing some stucco prep work on the rear wall.  We're adding weep screed all around.  It's a good improvement.

Another picture of the sewer clean-out pit.  The diagonal pipe is the line from the house.  The vertical is the clean-out.  The two join with the sewer utility.  I believe this is supposed to be terra cotta.

Final prep for the stucco on the south side.  Looks good.


The family room is nearing completion of its wallboard.  The wall on the left is getting special QuietRock wallboard.  This is to minimize noise transfer to Cali's room.


My sister checking out the progress in the master bathroom.

The stucco prep crew working on the south side.  The scratch coat is scheduled for tomorrow.

I believe the family is done or nearly so.  Ready for taping.

Back to the rear wall.  They are moving quick.

They are tying in the wire.

We are getting 'square' corners on the stucco.  They attach special square corner wire for that purpose.

Every outside corner gets special treatment.  This guy was very careful in his work.  He used a level to make sure his corner wire was attached right!

Tuesday, January 1, 2013

January 1, 2013: More progress on the wallboard

And digging up the sewer clean-out...

The living room has been boarded.  This is from the dining area looking towards the front window.

Living room again.  This time from the clipped corner towards the fireplace.

The kitchen.

This is the skylight in the master bath.

The master bedroom closet.

This is the guest bedroom shower.  We're finalizing the tile.

Digging down to the sewer.  I think it's going to need to be changed out for modern materials.  It's way down.  Probably 8 feet.

Saturday, December 29, 2012

December 29: Wallboard has started

A team of two started upstairs during between Christmas and new years.  They did the closet in the master bedroom first.

This is Evan digging out the sewer cutout.

Back to the upstairs.  The wallboard is going up quick.  It's a very dusty job.  The snowy look to the picture is the wallboard dust floating in the room.

This is the master bathroom.  The shower is not yet done.

The wallboard is going over the internal sheer wall.  The studs to the right of the sheer wall were furred to match.

They've gone home for the day.  Getting very close to complete.

The shower has some green board up now.

A diversion... These are the vent stacks for the stove exhaust.  Two 8" pipes.

The wallboard team moved down stairs to the living room.  Ceiling first, I guess.

These guys move quick.  They are doing a good job.

Sunday, December 23, 2012

December 23: Wallboard preparation

PG&E marked the location of the utilities on the ground. The yellow is the path of the gas line.

The yellow dashed line where the gas line runs under the front yard.  The white square (and line?) is where the sewer cut-out needs to be dug.

A closer view of the gas termination.

The ceiling Beth's office is insulated.  Cali is standing in the hallway next to the stairs.

We added blocking in between studs in areas that we might be mounting art.  This is the stairwell.

This is the master bedroom.  How did they get those sheets of wallboard up here?

The family room loaded with wallboard ready for the post-christmas installation.

This is the blocking for the TV wall mount.

We added some blocking in front of the armor plating.

Some blocking above the fireplace.  We wrote down the centers (height from floor) on the plans that Cali is holding.

This is the wall behind the fireplace.

This is the wall behind the powder room.

This is the wall between the two windows in the living room.

This is the powder room.  The blocking here is for the TP holder.  I think all bathrooms got TP holder blocking.

This is the wall opposite the patio doors in the family room.

This is the wall to the right of the kitchen in the family room.  I wanted to capture where the strapping and plates were located.