Thursday, January 3, 2013

January 3, 2013: Stucco prep and more wallboard

Evan doing some stucco prep work on the rear wall.  We're adding weep screed all around.  It's a good improvement.

Another picture of the sewer clean-out pit.  The diagonal pipe is the line from the house.  The vertical is the clean-out.  The two join with the sewer utility.  I believe this is supposed to be terra cotta.

Final prep for the stucco on the south side.  Looks good.


The family room is nearing completion of its wallboard.  The wall on the left is getting special QuietRock wallboard.  This is to minimize noise transfer to Cali's room.


My sister checking out the progress in the master bathroom.

The stucco prep crew working on the south side.  The scratch coat is scheduled for tomorrow.

I believe the family is done or nearly so.  Ready for taping.

Back to the rear wall.  They are moving quick.

They are tying in the wire.

We are getting 'square' corners on the stucco.  They attach special square corner wire for that purpose.

Every outside corner gets special treatment.  This guy was very careful in his work.  He used a level to make sure his corner wire was attached right!

No comments: