Wednesday, September 19, 2012

Sept 19: inside and outside plumbing, fireplace and solar

While I've been researching the components for the home theater, specifically speakers, more progress on the house has happened.  I need to select the in-ceiling surround speakers so that they can get installed before the sheetrock gets installed.  We've had:
  • Shower controls installed
  • fireplace installed
  • Some of the power has actually been hooked up and tested
  • The solar inverter and cabling was installed.
The master bath shower control.

The girls bath shower control.  The tub is under the plywood.

OK, this is annoying. This picture needs to be rotated 90 degrees  clockwise, but I don't see a method to do that. This is the main water input.  It's a bit confusing, but the pipe at the bottom appears to be the input.  Looks like simple 1" PVC.


This is Rick.  I used to work with him at Quantum when he was a software developer.  After Quantum was sold he started his solar power company.  I was one of his early customers.  Here, he has reinstalled the Sunnyboy inverter (red box).

Cali enjoying the new fireplace.

The fireplace from the front.

This looks like gas and galvanized plumbing parts.

The plumbing for the clothes washer.  The solar inverter is installed on the other side of the wall.

The curious pipage to avoid the silver A/C pipe.

Reconnecting up the outside plumbing.

This is the same water pipe that snaked around the house in the prior picture.

I think this was an accidental pic, but is shows the current state of the left side of the house.

That power is for the outside lighting.